Blake's Eagle Project
Time Line of my Eagle Project
Broke Ground - July 11, 2009
Poured Concrete - July 18,2009
Completed Project - July 25, 2009
Important Links:
SCIRA, Inc.
Alex's Tower Construction Eagle Project